Nuclear is nothing bog standard. If it was, it wouldn't take 10 years. Almost every plant is a boutique job that requires lots of specialists. The Westinghouse AP1000 reactor design was meant to get around this. It didn't.
The experts can stay where they are: maintaining existing nuclear power.
Renewables don't take much skilled labor at all. It's putting solar panels on racks in a field, or hoisting wind blades up a tower (crane operation is a specialty, but not on the level of nuclear engineering).
China built a few Ap1000 designs. The Sanmen station started in 2009 with completion expected in 2014 (2015 for the second unit). It went into 2019. The second, Haiyang, went about the same.
This is pretty similar to what happened in the US with Volgte.