Green energy plan needs 600 miles of power lines
Green energy plan needs 600 miles of power lines
www.bbc.com Green energy plan needs 600 miles of power lines - report
Energy planners say Labour's 2030 electricity net zero target is "achievable" but a "huge challenge".
Nearly 620 miles (1,000km) of new power lines need to be built to meet the government's clean energy plans, official energy planners have concluded.
In a report, the body in charge of linking new projects to the grid said Labour's target to decarbonise electricity by 2030 was "achievable" but a "huge challenge".
It will warn that infrastructure for the electricity network will need to be built much faster than it has been over the last decade to meet the pledge.
Energy Secretary Ed Miliband said ministers were committed to "significant reforms" of the planning system to speed up new connections.